India faces power shortage risks amid depleting coal stocks and thermal capacity constraints


NEW DELHI: India is facing a looming power shortage driven by a scarcity of baseload thermal capacity and rapidly depleting coal stocks at power plants, prompting high-level meetings at the Centre and urgent procurement efforts by states.
States across the country have been directed to secure electricity at all costs, triggering a surge in short-term power procurement tenders. According to data from the Ministry of Power’s DEEP portal, at least five states (including Tamil Nadu, Kerala, Rajasthan, and Gujarat) alongside private distribution utilities have floated tenders to secure additional electricity for January, February, March, April, May, and June-July next year. Uttar Pradesh is also learnt to be vying for additional power ahead of state elections early next year.
Private distribution companies, such as Noida Power Company Ltd and Adani Electricity Mumbai Ltd, have floated tenders where discovered prices touched Rs 19 to Rs 20 per unit. While standard spot prices are capped at Rs 10 per unit, rates can climb up to Rs 20 per unit in the specialized High Price Day-Ahead Market.
Grid India’s daily frequency profile data shows that real-time grid frequency is falling below the mandated lower limit of 49.9 Hz during solar hours, with even more precipitous drops during non-solar evening hours when solar generation is unavailable.
Coal inventories at thermal power plants have fallen sharply, declining by about 66% between April and September this year, compared to a 23% drop during the same period last year. As of November 15, total inventory at domestic coal-based plants stood at 20.79 million tonnes, down from approximately 55 million tonnes at the beginning of April. Officials in the Ministry of Power have stated that rebuilding coal stocks ahead of next summer is a primary objective.
To address the inventory crunch, the government is discussing measures to expand coal storage capacity beyond normative requirements. While the standard normative requirement is approximately 59 million tonnes, existing thermal plants have a storage capacity of up to 80 million tonnes, equivalent to roughly 30 days of consumption. Discussions are underway to potentially double storage capacity to 160 million tonnes to provide up to 60 days of reserves, though such an expansion would require additional physical storage space.
The current vulnerability stems partly from past policy decisions. The Union Power Ministry’s National Electricity Plan for 2017-22 ruled out fresh thermal capacity additions beyond 2022, aside from 50 gigawatts of projects already under construction, shifting focus primarily toward renewables.
Addressing the capacity gap, Central Electricity Authority chairperson Ghanshyam Prasad flagged the need to add 105 to 150 gigawatts of coal-based power capacity by 2035 during an October 13 meeting, exceeding the 97 gigawatts currently planned.